WORKS & INFRASTRUCTURE

  • Home
  • Project Details
08 Nov

WORKS & INFRASTRUCTURE

WORKS & INFRASTRUCTURE

Infrastructure consolidation and expansion is one of the cardinal objectives of the present administration. With a budgetary allocation of N65.42 Billion in the 2015 state appropriation and N91.8 Billion in 2016, infrastructural development and the construction of roads, bridges and drainages have remained at the centre stage of the Udom Emmanuel administration. This is especially so, as they are key drivers of industrialization and Investors and tourists are best attracted to destinations where adequate infrastructure and corresponding good network of roads and other related facilities are put in place. To this end, with over 160km of roads spread across the state, government has continued to vigorously tackle works and infrastructure with the following attendant achievements:


  • Emergency Intervention on Gully Erosion ravaging Calabar – Itu Road at Enen Atai, Itu Local Government Area by Direct Labour Work.
  • Emergency Intervention on Gully Erosion ravaging the School of Nursing, Anua by Direct Labour.
  • Construction of 3.5km Ikot Udom Road with 15m Span Bridge in Ibiono Ibom Local Government Area.

–  7.3m carriageway width.
–  Side Drains.
–  150mm crushed stone-base base course.
–  50mm hot roll asphaltic wearing course.
–  15m span bridge.
–  Outfall at designated points.

Benefit:     Opening of Ikot Udom axis of Ibiono Ibom Local Government Area.

  • Construction of 5km Ikot Usop – Ikot Edeghe – Ikot Ekpuk Road with 30m Span Bridge in Mkpat Enin Local Government Area.

Scope of Work:

–  7.3m carriageway width
–  Side Drains.
–  Sharp sand sub base/base courses.
–  150mm crushed stone-base base course.
–  50mm hot roll asphaltic wearing course.
–  30m span bridge.
–  Outfall at designated points.

Benefit:     Linking up the Ikot Usop axis to the Ikot Ekpuk end of Mkpat Enin Local Government Area.

  • Construction of 5km Mkpok-Okat Road in Onna Local Government Area.

Scope of Work:

–  7.3m carriageway width.
–  Side Drains.
–  150mm Crushed stone-base base course.
–  50mm hot roll asphaltic wearing course.
–  Outfall at designated points.

Benefit:     Linking the Mkpok – Okat axis of Onna Local Government Area to the East-West Road and boosting of economic activities.

  • Emergency Works in the completion of Outfalls and Urban Roads in Oron.

Scope of Work:

  • Completion of ongoing 7.3m carriageway width of roads.
  • Construction of underground outfall drains from   Mainland Lane/Avenue through Bassey Lane,     Effiat Street/Lane to Anwana Esin/Mary Hanney Road with extension to the lowest erosion plain behind Asbestonit Complex.
  • Underground outfall drain, from Convent Street through post Office Road to Anwana Esin by Oron Road, discharging into the existing outfall down Iyamba Creek.
  • Sharp sand sub base/base courses.
  • 150mm crushed stone-base base course.
  • 50mm hot roll asphaltic wearing course.
  • 15m span bridge.

Benefit:     De-flooding of the affected areas in Oron Urban and completion of on-going of Oron Urban roads affected by the outfall construction.

  • Construction of Uyo outfall drain from Nsikak Eduok/Oron Road to Tropicana Complex, Uyo.s

Scope:     

  • 5 Km total length of 2.0m x 1.5m Double Cell underground Drain.
  • 5 Km Service Road.

Special Benefit:   De – flooding of about 3.5 Square kilometer of water – shed area which includes:

  • Part of Ewet Housing Estate
  • Part of Osong Ama Housing Estate
  • Part of Edet Akpan Avenue and Oron Road
  • Akwa Efak Itiam Ikot Ebia and Itiam Etoi Communities, etc.
  • Dualization of Uyo-Etinan Road

Scope: 

  • 7km
  • 260m Dualized Bridge/Interchange
  • 200mm Lateritic Sub-Base Course
  • 200mm Crushed Stone Base Course
  • 60mm Asphaltic Bonder Course
  • 50mm Asphaltic Wearing Course
  • 0m Carriageway and 2.75m hard Shoulder on each side
  • Designated Concrete Outfall Drains
  • Reinforced Concrete Side Drains

Special Benefits:

  • Urban renewal/regeneration & beautification
  • Elimination of urban flooding
  • Free flow of traffic
  • Promotes economic activities and social interactions
  • Reduction in the incidences of traffic accidents
  • Construction of Etinan-Ndon Eyo Road with 2No. Bridges and Spur

Scope:

  • 4km
  • 2km Dualized Road
  • Dualized Bridges
  • 2km Single Carriageway Road
  • 200mm Lateritic Sub-Base Course
  • 200mm Crushed Stone Base Course
  • 60mm Asphaltic Binder Course
  • 50mm Asphaltic Wearing Course
  • 0m Carriageway and 2.75m Asphaltic Shoulder on each side
  • Side Drains and Walkway in Urban Centers

Special Benefits

  • Urban renewal/regeneration & beautification
  • Opening up of hitherto inaccessible communities
  • Elimination of flooding and erosion
  • Free flow of traffic
  • Promotes economic activities and social interactions
  • Reduction in the incidences of traffic accidents
  • Construction of Ebekpo-Ikot Ebidang Road

Scope:

  • 3km
  • 200km lateritic sub base course
  • 200mm Crushed Stone base course
  • 50mm Asphaltic wearing course
  • 3m single carriageway with 1.5m hard shoulder on both sides of the road
  • Reinforced concrete outfall drains

Special Benefits

  • Urban renewal/regeneration and beautification
  • Access to areas that were hitherto inaccessible communities
  • Access to a proposed clay factory at Ikot Ebidang
  • Access to the beach at the shore of the Atlantic Ocean
  • Free flow of traffic
  • Elimination of flooding and erosion
  • Promotion of economic activities and social interactions
  • Construction of new Terminal Building at the Ibom International Airport.
  • Construction of the second runway/taxiway as well as the Maintenance, Repair and Overhaul (MRO) facility.
  • Commencement of design work of the ground/first floor at the Ibom Tropicana entertainment complex, Uyo.
  • Commencement of the furnishing of Ibom Tropicana complex.

(A) DUALIZATION OF EKET-IBENO ROAD 

                PROJECT STATUS

The project entails the construction of a dual carriage road linking Eket Township to Ibeno Township. The major details are as follows:

1.Total Length of Road = 19.5kilometre

  1. The road pavement comprises of the followings:
  2. Dual carriageway with each carriageway width=9.3m
  3. 300mm thick stone base material as base-course
  4. 150mm thick sharp sand filling as sub base course
  5. 60mm thick Asphaltic Binder Course
  6. 40mm thick Asphaltic Wearing Course
  7. Major Features are 6No. Bridges as follows:
  8. 4No. 20m Span Reinforced Concrete Bridges at 2N0. Locations (2No. per location)
  9. One 100m long Reinforced Concrete Bridges
  10. One 200m long Reinforced Concrete Bridges


(B) 

S/NDESCRIPTIONPROGRESS STATUSUNITQTY APPROVEDQTY DONE% COMPLETED
1Setting outComplete from CH4+025-CH19+458km19.5015.4379.14
2Site ClearingCompleted from CH4+300-CH19+458km19.5015.1677.73
3Sub-gradeCompleted from CH4+300-CH7+800(LHS)

Completed from CH8 +100-CH18+000(LHS)

km19.5013.4045.81
4Sub-baseCompleted from CH4+300-CH7+800(LHS)

Completed fromCH8+800-CH18+000

km19.508.2342.18
5.Stone BaseCH4+500-CH5+800 (LHS)km19.509.2047.18
       
6Prime CoatCompleted from CH9+500-CH17+400 (LHS)km19.509.2047.18
7AsphalticCompleted from CH11+100-CH15+380 (LHS)

Completed from CH15+800-CH17+375 (LHS)

km19.506.4516.54
8Concrete DrainsCompleted length is 35 Nosm6875.004285.0062.33
9CulvertCompleted 35 NosNo35.0035.0035.00
10Bridges1. Completed soil investigation for 4 bridges

2.Completed 2 old bridges

3. Marine bridge completed

4 Completed precast beams & pilling work for Ebanna bridge

5. Completed 2 abutments for Ebanna bridge

6.Completed one span & precast beam for Ukpenekang bridge

No4.001.8045.00

 

 

 

CONSTRUCTION OF 6.41 KM NTO EDINO – EKWERE AZU ROAD WITH 2NOS 45M SPAN BRIDGES IN OBOT AKARA LOCAL GOVERNMENT AREA

1.0    SCOPE OF WORK

  • 41 km Road
  • (15m x 3) 45m Span Bridges
  • 150mm Lateritic Sub-base Course
  • 150mm Crushed Stone Base Course
  • 50mm Asphaltic Binder Course
  • 40mm Wearing Course
  • Reinforced Concrete Side Drains and Culvert at designated locations
  • Stone Pitching
  • Grassing
  • Road Marking and Painting

2.0   PROGRESS OF WORK

S/NoWork DescriptionChainageDistance (m)
  1.Desilting of swamp and pumping

of sharp sand from river into desilted

areas.

0+700 – 1+175475
  2.Building up of road formation on the

filled areas to required formation level

using approved material.

0+700 – 1+175475
  3.Stripping of vegetation/removal of

unsuitable material to average depth of

750mm.

1+800 – 2+500700
  4.Cutting to reduce the hill and hauling

material to fill portion

1+800 – 2+500700
  5.Filling with approved material/excavated

area of unsuitable material and building

up of road formation to sub-base level.

0+700 – 1+175475
  6.Stripping of vegetation/removal of

Unsuitable.

3+900 – 5+700700
  7.Backfilling excavated portion and

raising formation to sub-base level

using approved material.

3+900 – 5+700700
  8.Clearing of remaining stretch to

required width to the boundary.

4+750 – 5+700950

 

S/NoWork ItemPercentage Completion (%)
1.Mobilization of equipment and materials Required to site.100
2.Setting-Out100
3.Compensation25
4.Site Clearance89
5.Excavation of unsuitable materials70
6.Filling from borrow-pit material60
7.Laying and compaction of sub-grade70
8.Laying and compaction of sub-base60
9.Laying and compaction of stone-base0
10.Spraying of prime coat0
11.Laying of asphaltic binder course0
12.Laying of asphaltic wearing course0
13.Bridge Works0
14.Construction of drains/culvert0
15.Stone Pitching0
16.Grassing0
17.Road Marking and Painting0

 

 

CONSTRUCTION OF IKOT USOP-IKOT EDEGHE-IKOT EKPUK ROAD WITH A 30M SPAN BRIDGE IN MKPAT ENIN LOCAL GOVERNMENT AREA

 

(A) SCOPE OF WORK

  1. 5.0 Km Road
  2. 30m Span Bridges
  3. 150mm Lateritic Sub-base Course
  4. 150mm crushed stone Base Course
  5. 50mm Asphaltic Binder Course
  6. Reinforced Concrete Side Drains and Culvert at designated Locations
  7. Stone Pitching at Critical area
  8. Grassing
  9. Road marketing and painting

 

(B)  PROGRESS OF WORK

S/No    WORK ITEM% COMPLETED
1.Mobilization of equipment and materials Require to site     100
2.Setting-out100
3.Compensation100
4.Site Clearing100
5.Topsoil removal and excavation of unsuitable materials100
6.Filling from borrow- pit material80
7.Laying and compaction of  sub-base80
8.Laying and compaction of sub-grade80
9.Laying and compaction of stone- base0
10.Spraying of prime coat0
11.Laying of asphaltic binder course0
12.Laying of asphaltic wearing course0
13.Bridge works0
14Construction of Culvert100
15.Construction of drains5
16.Stone Pitching0
17.Grassing0
18.Road marketing and painting0

 

DUALIZATION OF 28KM UYO-ORON ROAD (AIRPORT ROAD-OKOPEDI ORON RD EAST-WEST) RD PHASE 1 (14.5KM)

 

(A) SCOPE OF WORKS

  1. Dualization of 28.0km
  2. 60m Span Bridge
  3. 150mm Laterite Sub-base

4.150mm sand-cement stabilized sub-base

  1. 60mm Asphaltic Concrete Wearing Couse
  2. 7.3m Dual Carriageway width, and 2.75m Shoulders (Surface Dressing)
  3. 0.6m concrete crash median barrier
  4. Reinforced concrete side drains/ culverts at designated locations
  5. Concrete outfall drains
  6. 2No. Roundabouts
  7. Street Light
  8. 35m Span Triple Cell Culvert

(B)  PROGRESS

 

S/NO      WORK ITEM% COMPLETION
1.Mobilization of equipment and materials require to site10
2.Setting-out Ch0+000-Ch14+500100
3Site clearing Ch0+000-Ch14+500100
4Compensation0
5Excavation of unsuitable materials0
6Filling from borrow pit material0
7Laying and compaction of stone base0
8Laying and compaction of sub base0
9Spraying of prime coat0
10Laying asphaltic binder course0
11Laying asphaltic wearing course0
12Erection of bridge0
13Construction of drains/culverts0
14Relocation of utilities0

 

CONSTRUCTION OF 4.6KM SCHOOL OF ARTS AND SCIENCE ROAD, NUNG UKIM, IKONO L.G.A.

 

          (A) SOPE OF WORK

  1. 4.6km Road
  2. Laterite subgrade/sharp sand replacement where necessary
  3. Laterite sub-base 150mm
  4. 150mm crush stone base course
  5. Reinforced concrete line drain throughout the stretch
  6. Outfall drains at designated location
  7. 50mm asphaltic wearing course
  8. Repairs/overlays of entrance to the school

 

(B)  CONTRACTOR’S PROGRESS OF WORK

S/N    WORK ITEM& COMPLETION
1.Mobilization of equipment material to site50
2.Site clearance75
3.Excavation of unsuitable materials0
4.Filling from borrow-pit material